HEMP MORTARS using St. Astier Natural Limes
Hemp is a natural material suitable for making light weight insulating mortars. Its density vary between 110 and 150 kg. per m3. The strands are between 5 and 25mm long. The thermal conductivity of hemp is 0.05 W/m.K.
Particular attention has to be paid in making sure that hemp is not subject to dampness either due to stocking conditions of the raw material or capillary action in hemp mortars (adequate damp courses if constructing walls or insulating/draining ballast base in concrete should be in place).
The qualities of St. Astier natural hydraulic limes are ideal for making
hemp mortars. A special binder (Batichanvre) has been prepared for making
Hemp mortars
INSULATING HEMP/LIME CONCRETE
Dosage: 1 bag of Batichanvre ( 35kg.) + 100 litres of hemp + (optional) 5 litres of coarse sharp sand (5mm down)
Water addition : 35 to 40 litres
|
|
Application
Directly on soil: on a well levelled and compacted soil, if necessary stabilised **, construct a 15-20cm. ballast base.
Do not use any plastic sheeting.
On wood: provide a 2 cm. layer of hemp directly on the surface without plastic sheeting.
Apply the hemp concrete in layers of 5 cm. maximum and level with a rake. Compact by tamping. To obtain the highest thermal insulation this first layer should not be compacted (this will be suitable in loft insulations where the highest compressive strength is not required). The final layer will be levelled with a straight edge, compacted and floated with a wooden float.
The minimum thickness of the hemp/lime insulating concrete is 8 cm. At this thickness the thermal conductivity of the concrete will be between 0.11 to 0.13 W/m.K depending on the compaction. The compressive strength at 90days will be about 1.8 N/mm2.
The production is 800 to 850 litres of mortar per m3 of hemp + 10 bags of Batichanvre, depending on compaction.
Tiles, wooden floors or carpeting can be laid on a further 4cm. lime concrete screed suitably finished after the total drying of the work (up to 90 days depending on thickness and climatic conditions). Keep area well ventilated and avoid forced drying.
** Soils can be stabilised by rotovating 200kg. of NHL 5 to 1m3 of damp soil. Extra water can be added in dry soil. Do not saturate to avoid a longer drying time.
HEMP MORTARS using St. Astier limes Walls construction Timber framed walls Fix 2 x 2 wooden battens at the middle of each frame. Walls Construct shuttering to allow for the required thickness
of the final render/plaster. |
![]() |
![]() |
Shutterings max. 1 m. high. Once completed the first level, fix the second level panels and apply a second layer of mortar, about 25cm. and compact. Only then the lower panel can be removed. The first level mortar has to remain enclosed for min. 30 minutes. Apply same method to the remaining levels. If a plaster or render is going to be applied, movement joints should be used every 9m2. |
Dosage, mixing ,water addition and production: as per hemp/lime concrete
External render and internal plasters:
Use NHL 2 for base and finishing coat once the structure is completely dry (approx. 60-90 days depending on weather conditions and thickness). Protect external work from adverse weather conditions. Internal plaster should at all times have a NHL 2 base coat before different finishes, if required, are applied (EcoMortar F, fine plasters, lime paints etc..).
Maximum areas allowed: 3m2 for wooden frames and 9m2 for walls
LOFT INSULATION MORTAR
This lightweight mortar does not have high mechanical performance.
Mixing: in paddle or drum mixers (same procedure as described in the Hemp/Lime concrete section).
Dosage: 1 bag of NHL 2 (or 1 bag of Batichanvre) + 200 liters of Hemp + 35-40 liters of water.
Consumption: 1m3 of insulating mortar requires 1.05 m3 of Hemp and 5.25/5.5 bags of NHL 2 or Batichanvre.
Thermal conductivity of this mortar is: 0.09W/m.K.
Application: loosely apply about 2 cm. of dry hemp between the floor timbers. Place the mortar above this layer at a thickness of min. 15 cm./max. 25 cm. Make sure that the hemp mortar level is about 1 - 2 cm. over the final required level to allow for compaction. Lightly compact the mortar to bring it to the required level. If a floor is required, make sure that there is a space of about 2 cm between the top level of the insulating mortar and the floor boards
INTERNAL WALLS INSULATING RENDER
On a properly prepared dry background apply a stipple coat as follows:
1 volume of NHL 5 to 2 volumes of coarse sharp sand.
The hemp/lime mortar can be applied wet on wet (after 12 hours or so) by laying on or casting on.
The hemp/lime mortar dosage for a natural finish is:
2 bags of NHL 2 + 100 litres of hemp + 60/70 litres of water
The thickness of the render averages 5cm (up to 8cm.). It is applied in layers of 2-3 cm. at about 20 to 90 minutes interval between each pass. The last coat (2 cm.) to be applied 24 - 48 hours after the previous coat. This coat will be floated to achieve the required finish. Consumption: 27kg of NHL2 + 55 liters of Hemp for 1 m2 of render @ 5cm thickness.
If a decorated finish is required use Batichanvre instead of NHL 2 and proceed as above. The decorative finish (lime wash, Ecomortar, stucco etc) can be applied after a drying period of 45-90 days. Consumption: 38.5kg of Batichanvre + 55 litres of Hemp for 1m2 of render @ 5 cm. thickness. The thermal conductivity of the above renders will be between 0.11 to 0.13 W/m.K. The density of this mortars will be between 0.75 and 0.85 kg. per litre, depending on the compaction
In all cases the surfaces should not exceed 15m2 without movement joints. Walls should have a damp course to avoid moisture transfer by capillary action.
The information supplied in this document is for general guidance
only.
It is recommended that test panels are constructed in all cases
For further Guidance, contact your St Astier Distributor.
Copyright © Setra Marketing Ltd. 2006




